I agree with Jame's point of view Mike.
I would like to add that, photovoltaics are not toys to be trifled with. They can produce a serious amount of electricity that, if not conducted properly, can cause a fire.
The NEC - National Electrical Code is an institution (for lack of a better word) of the NFPA - National Fire Protection Association.
http://www.nfpa.org/index.aspThat "bunch of old solar panels" you mention, if "wired" together a certain way, might have the potential to weld steel together. It all depends really on just how many a "bunch" is and what the specifications are. All of the PV modules ratings, not just volts, is the first thing an electrician would look at. He or she would need to know all of those ratings before any calculations could be made for sizing the electrical components for the rest of the system.
Wire size is typically based on the expected amperage to be conducted over them but * it can also be based on such things as voltage drop over the length of the wire, as well as the type of insulating jacket it has and the location where it is intended to used.
There should be a label on the back of your PV modules that shows several "ratings" at a STC. - Standard Test Condition.
Pmax-
Vmpp-
Impp-
Voc-
Isc-
One in particular is the Isc or Impedance short circuited or in a more familiar term, Amperage short circuited. UL - Underwriters Laboratories, requires an additional 125% be added to this Isc rating. The NEC requires an additional 125% to that. So if a PV modules has an Isc rating of 4.75 amps for example, 156% of that amperage must be added back to that amperage and that is where calculations for wire size, based on amperage, starts for a PV source circuit. 125% x 125% = 156%
4.75 x 156% = 7.41 So, based on that example of Isc 4.75, 7.41 amps is used to start calculations for wire size, based on amperage, not just the Isc of 4.75 or the lesser rating Impp. This just scratches the surface! Believe it or not, ambient temperatures can take a part in these calculations.
Now, perhaps, you can begin to see why electrical contractors require an Electrical Contractors License and why permits must be issued followed up by inspections from the; city, county, or state which ever one holds jurisdiction over the location of a proposed job?
http://photovoltaics.sandia.gov/In particular,
http://photovoltaics.sandia.gov/docs/John_Wiles_Code_Corner.htmI can only guess but it would seem to me that this would make getting a "sweet" price on the PV modules even "sweeter."